CLAUSE I.115 – DEAR 970.5231-4 PREEXISTING CONDITIONS (DEC 2000) (ALTERNATE II) (DEC 2000)

 

(a)        The Department of Energy agrees to reimburse the contractor, and the contractor shall not be held responsible, for any liability (including without limitation, a claim involving strict or absolute liability and any civil fine or penalty), expense, or remediation cost, but limited to those of a civil nature, which may be incurred by, imposed on, or asserted against the contractor arising out of any condition, act, or failure to act which occurred before the contractor assumed responsibility on January 1, 2007. To the extent the acts or omissions of the contractor cause or add to any liability, expense or remediation cost resulting from conditions in existence prior to January 1, 2007, the contractor shall be responsible in accordance with the terms and conditions of this contract.

(b)        The obligations of the Department of Energy under this clause are subject to the availability of appropriated funds.

(c)        The contractor has the duty to inspect the facilities and sites and timely identify to the contracting officer those conditions which it believes could give rise to a liability, obligation, loss, damage, penalty, fine, claim, action, suit, cost, expense, or disbursement or areas of actual or potential noncompliance with the terms and conditions of this contract or applicable law or regulation. The contractor has the responsibility to take corrective action, as directed by the contracting officer and as required elsewhere in this contract.